As a supply chain management and sourcing company, we not only face the situation of helping our clients develop new parts with our multi-process collaborative experience but also often encounter some clients who want to change the original production process of their parts to achieve the purpose of cost reduction.

Here are 3 main factors that we have to consider when we want to make a part by sintering technology.

1. Material selection

Choose iron-based, copper-based, or stainless steel-based material according to your requirement.

Macro(apparent)hardness 20~25 HRC,density 5.8~8.3 g/cm³,tensile strength maxmium 225,000 psi/1550 Mpa.

The 3 most common material standards:

MPIF 35, US standard

Common format: FC-xxxx, example: FC-0205, means 2% Cu, 0.5% C.

CNC milling machine cutting a part at Chau Minh Long, a DEWIN-audited Vietnamese factory

Cutting and drilling equipment at Tbd Casting, a DEWIN-audited Vietnamese factory

Die casting machine at VISION, a DEWIN-audited Vietnamese factory

DIN 30910, German standard

Common format: Sint-X00, example: Sint-C11, means 1~5% Cu, 0.4~1.5% C.

CNC milling machine cutting a part at Nhat Minh Tt Jsc, a DEWIN-audited Vietnamese factory

JIS Z2550, Japan standard

Common format: SMF-xxxx, example: SMF-4050, means 1~5% Cu, 0.2~1.0% C.

If you know a similar material code on your old drawings from the engineering or design company, it is easier to start the work to request for quotation.

If not, welcome to leave a message to me, I’ll reply to you with my advice soon.

2. Structure design

To revise the design suitable for sintering production.

Industrial welding station at ALUGOS COMPANY LIMITED, a DEWIN-audited manufacturing facility

2.1

Because the profile and sizes are provided by mould, the compacting direction is up and down, if there’s a horizontal hole design, we have to drill it by post-machining, it will reduce the production efficiency and increase the extra cost.

Production floor at Happyco, a DEWIN-audited Vietnamese factory

2.2

For the thin-wall part, the single sidewall thickness must be over 1.5~2 mm.

2.3

Design draft angle 5~15°for the vertical face to help the demoulding and avoid the post-machining process.

2.4

You can evaluate a rough value for the required production equipment.

To compact a green part with targeted strength, every square centimeter will require 4~7 tons’ force by the pressing machine.

If the supplier doesn’t have such a big pressing machine, he maybe is telling a lie to you or outsourced the pressing process to other factories.

Coordinate measuring machine used for dimensional inspection at Kinzoku Vietnam Industrial, a DEWIN-audited Vietnamese factory

Our engineer will provide professional advice for design optimization.

3. Cost-effective

CNC lathe in production at Dai Anh Phat Mechanical, a DEWIN-audited Vietnamese factory

The approximate mould cost investment will be $1000~$20,000 depended on the size of the parts.

The sintering technology can provide a daily output of up to 15,000 pieces per mould, and very good dimensional consistency provided by mould.

But we have to consider the average mould cost for every part before you make the decision to convert the original technology(pure machining, casting, forging, stamping, etc) to sintering.

Get in contact with us if you need a proposal for sintering parts.

Video: Sample metal parts from audited Vietnamese factories in the DEWIN network. (@dewintech)

Precision Manufacturing & Sourcing Specification Matrix

Technical DimensionStandard Commercial GradeHigh-Precision OEM Export GradeDEWIN Verification Protocol
Machining & Forming ToleranceISO 2768-m (±0.10 mm nominal)ISO 2768-f (±0.01 mm – ±0.025 mm critical bores)Calibrated 3D CMM & Air/Pin Gauging
Surface Roughness & FinishRa 1.6 – 3.2 µm as-machined / standard coatRa 0.4 – 0.8 µm precision ground / MIL-A-8625 anodizedProfilometer & Coating Thickness Gauge
Material & Alloy CertificationSupplier Mill Test Report (MTR)Independent OES chemical & mechanical verificationEN 10204 3.1 + RoHS/REACH Compliance
Batch Inspection & PackagingISO 2859-1 (AQL 1.0 Major / 2.5 Minor)Zero-defect critical features + VCI export cratingPre-Shipment Inspection (PSI) Report

Frequently Asked Questions

What engineering files are required to quote 3 factors we have to consider when making a part by sintering with DEWIN?

Provide 3D CAD models (STEP or IGES) along with 2D engineering drawings (PDF/DXF) specifying critical-to-quality (CTQ) tolerances, material grade, surface finish, and annual volume.

How does DEWIN verify dimensional accuracy and material compliance before shipment?

Every production lot undergoes incoming material spectrometer verification (EN 10204 3.1), First Article Inspection (FAI) via 2D/3D coordinate measuring machines (CMM), and AQL pre-shipment audits.

Can DEWIN support both low-volume prototype validation and mass production scaling in Vietnam and China?

Yes. DEWIN coordinates rapid CNC and bridge-tooling prototypes alongside high-tonnage production tooling across audited ISO 9001 and IATF 16949 partner factories in Vietnam and China.

Manufacturing RFQ

Have a STEP Model or 2D Drawing for This Project?

Share your drawing, material, quantity and finishing requirements to begin a manufacturing quote. Confirm pricing, delivery and inspection requirements during the review.

Upload CAD & Get Quote →