Every year around January, our Vietnam office starts fielding urgent calls from U.S. buyers who just realized their Q1 stamping parts orders are in jeopardy.
Lunar New Year (Tết) extends delivery times for stamping parts from Vietnam by 3 to 6 weeks beyond standard lead times. The disruption spans a 6-to-8-week window that includes a pre-holiday production slowdown, a 1-to-3-week factory shutdown, and a 2-week post-holiday ramp-up period with labor shortages and ocean freight congestion.
This is not a minor scheduling hiccup. It is a structural supply chain disruption that repeats every single year. Below, I will walk through the full timeline, the specific risks to stamped metal components, and the concrete steps we recommend to our clients so they can protect their production schedules.
How can I plan my stamping parts orders around Vietnam's Lunar New Year shutdown?
A lesson we learned early in our Vietnam operations is that planning for Tết cannot start in January. By then, most factory capacity is already spoken for, and the window for securing production slots has closed.
To plan stamping parts orders around Vietnam's Lunar New Year shutdown, place confirmed purchase orders by mid-December. Request your supplier's Tết production calendar 6 to 8 months in advance, add a 2-to-3-week buffer to standard lead times, and build safety stock to cover the full 6-to-8-week disruption window.
/12-05-2025-Pictures%20-%20Name/Hydraulic%20press%201.jpg)
Understanding the Three-Phase Disruption Window
The biggest mistake buyers make is treating Tết as a single holiday week. In reality, the impact unfolds in three distinct phases. Each phase creates its own set of problems for stamping parts procurement.
Phase 1: The Pre-Holiday Acceleration (Late December to Mid-January)
Factories rush to complete existing orders before workers leave. New orders are either rejected or pushed to post-holiday slots. Port congestion at Cat Lai 1 and Hai Phong builds rapidly as everyone tries to ship at once. Freight rates spike. Container availability drops.
Phase 2: The Shutdown (1 to 3 Weeks Around the Official Holiday)
For 2026, the official Tết holiday 2 runs February 17 through 24. But most stamping factories we work with close for longer. Some shut down as early as February 10 and do not reopen until March 3 or later. During this time, zero production happens. No quality inspections. No shipments.
Phase 3: The Post-Holiday Ramp-Up (Late February to Mid-March)
Workers migrate back slowly from rural provinces. Some do not return at all. Factories operate with skeleton crews. Manufacturing capacity sits at 50 to 70 percent for the first two weeks. Full normalization typically does not happen until mid-March.
A Practical Planning Timeline for 2026
| Milestone | Target Date | Action Required |
|---|---|---|
| Request supplier's Tết calendar | August 2025 | Get confirmed shutdown and reopening dates |
| Finalize Q1 production requirements | October 2025 | Lock in volumes and specifications |
| Place confirmed purchase orders | Mid-December 2025 | Secure production slots before cutoff |
| Ship pre-Tết orders | Late January 2026 | Clear all finished goods before port congestion peaks |
| Monitor supplier reopening | March 1–7, 2026 | Verify workforce return and production restart |
| Expect full normalization | Mid-March 2026 | Resume standard lead time planning |
Why Mid-December Is the Real Deadline
Our team in Vietnam coordinates directly with stamping plants across the country. When we ask factories about their order acceptance cutoffs, the answer is consistent: they stop taking new jobs 6 to 8 weeks before Tết. For 2026, that means the practical cutoff falls around mid-December 2025. Orders placed after that date face a high risk of being deferred to post-holiday production. This is especially true for custom stamping work 3 that requires tooling setup or progressive die adjustments. The lead time planning for stamping parts must account for this hard deadline, or you will find yourself waiting until March for parts you needed in February.
What delivery delays should I expect when sourcing stamping parts during Tet holiday?
One of our U.S. clients once assumed a 5-day delay for Tết and planned accordingly. The actual delay was 38 days. That experience shaped how we now brief every new customer on realistic timelines.
When sourcing stamping parts during Tết, expect delivery delays of 3 to 6 weeks beyond your standard lead time. These delays come from factory shutdowns lasting 1 to 3 weeks, port congestion adding 14 to 21 days, reduced shipping frequency with 10-to-14-day intervals between sailings, and post-holiday production backlogs.

Manufacturing Delays Specific to Stamping
Stamping parts are not like simple consumer goods that can be produced quickly with unskilled labor. Metal stamping requires trained press operators, die setters, and quality control inspectors. When these skilled workers leave for their hometowns during Tết, the factory cannot simply hire replacements.
Here is what happens inside a stamping plant during and after the holiday:
- Press operations stop completely. Heavy stamping presses need qualified operators. No operators, no production.
- Tooling maintenance fills the downtime. Many factories use the shutdown for annual die maintenance and progressive die repairs 5. If unexpected issues arise during maintenance, the production restart gets pushed back further.
- Raw material supply dries up. Domestic steel suppliers face their own Tết shutdowns. Blast furnaces and rolling mills need several days to reach operating temperatures after restarting. Steel coil delivery to stamping plants can be delayed by an additional week.
- Quality control bottlenecks emerge. With reduced QC staff in the first weeks after reopening, inspection throughput drops. For precision stamping with tight tolerances, this means slower release of finished goods.
Logistics Delays That Compound the Problem
The production backlog at the factory is only part of the story. The logistics chain from Vietnam to the U.S. faces its own set of Tết-related disruptions.
| Delay Factor | Normal Conditions | During Tết Period | Impact |
|---|---|---|---|
| Ocean freight sailing frequency | Weekly departures | Every 10–14 days | Longer wait for vessel space |
| Port congestion at HCMC/Hai Phong | 1–3 day processing | 14–21 day backlogs | Shipments stuck at origin |
| Container availability | Standard booking | Tight supply, high rollover risk | Bookings bumped to later sailings |
| Customs clearance | 1–2 business days | 3–7 days due to staff shortages | Customs clearance delays add up |
| Freight rates | Standard market rates | 15–30% premium | Higher landed cost |
The Hidden Bottleneck: Tier-2 Subcontractors
Something many buyers overlook is the role of Tier-2 subcontractors. Precision stamping parts often require post-processing such as plating, heat treatment 6, or powder coating. These finishing services are typically handled by smaller shops. And smaller shops close longer than large factories. Our Vietnam team has seen plating vendors remain shut for up to four weeks. Even if your stamping factory reopens on schedule, your parts may sit waiting for finishing work. This hidden bottleneck can add another 1 to 2 weeks of delay on top of everything else. Understanding the full metal fabrication lead times, including subcontractor schedules, is critical for realistic planning.
How do I communicate production schedules with my Vietnam supplier before Lunar New Year?
A trade-off we constantly weigh with our Vietnam-based suppliers is how early to start the Tết conversation without seeming premature. The answer, after seven years of managing these cycles, is that it is never too early.
To communicate production schedules with your Vietnam supplier before Lunar New Year, send a formal schedule request 6 to 8 months ahead. Ask for confirmed shutdown dates, last-order-acceptance dates, and expected restart dates. Use email with written confirmations rather than verbal agreements, and establish weekly check-ins starting 10 weeks before the holiday.

Why Written Communication Matters
Verbal assurances mean very little in the Tết context. We have seen cases where a factory verbally committed to a pre-holiday delivery date, only to miss it by two weeks because they over-committed their capacity. Every critical date must be documented in writing. Email confirmations. Updated production schedules. Shipping booking confirmations. Our Singapore office maintains a shared tracker with each Vietnamese supplier that logs every milestone date and its current status.
The Five Questions You Must Ask Your Supplier
Before Tết planning begins, send your supplier these five questions in a single, clear email:
- What is your exact shutdown period? Get the first day of closure and the first day of full production restart—not just the official holiday dates.
- What is your last date to accept new orders for pre-Tết delivery? This is your real ordering deadline.
- What is your expected workforce return rate? Some factories lose 10 to 15 percent of workers permanently after Tết. Ask about their historical retention.
- What is the status of raw material inventory? Confirm that steel coils and other inputs are already in stock or on order with sufficient lead time.
- What is your contingency plan for urgent orders? Some factories maintain skeleton crews for critical jobs. Others shut down entirely. Know which type you are dealing with.
A Communication Timeline That Works
| Weeks Before Tết | Communication Action | Purpose |
|---|---|---|
| 30–32 weeks | Send initial schedule request | Get shutdown dates and capacity outlook |
| 20–24 weeks | Confirm Q1 production volumes | Lock in production slots |
| 12–16 weeks | Issue formal purchase orders | Ensure materials are ordered |
| 8–10 weeks | Begin weekly status check-ins | Monitor progress and flag risks |
| 4–6 weeks | Confirm shipment bookings | Secure vessel space before congestion peaks |
| 2–3 weeks | Final pre-shutdown status call | Verify all open items are complete or tracked |
Bridging the Cultural Gap
One thing our team has learned from working on the ground in Vietnam is that Tết is not just a holiday. It is the most important cultural event of the year. Pressing a supplier to work through Tết or rush orders at the last minute will damage the relationship. Instead, show that you respect the holiday by planning early and communicating clearly. Suppliers who feel respected will prioritize your orders when capacity is tight. This approach to managing supply chain disruption through relationship-building has served our clients well, year after year.
What steps can I take to avoid stock shortages caused by Lunar New Year factory closures?
Last year, a purchasing manager at one of our key U.S. accounts told me he ran out of stamping brackets 7 in February and had to air-freight an emergency batch at five times the ocean freight cost. That single incident cost more than an entire quarter of careful inventory management would have.
To avoid stock shortages caused by Lunar New Year factory closures, start ordering safety stock 3 to 4 months before the holiday. Build a buffer inventory covering 8 to 10 weeks of demand. Diversify your supplier base to include factories with staggered shutdown schedules. Confirm all shipments are dispatched and cleared before port closures peak in late January.
/ICHI-%20Photo/150-ton%20Stamping%20Press%20Machine%201.jpg)
Building a Buffer Inventory Strategy
The core principle is simple: you need enough stock on hand (or in transit) to cover the entire disruption window plus a safety margin. For stamping parts, that window is 6 to 8 weeks. Add a 2-week safety margin, and you need 8 to 10 weeks of inventory coverage.
Here is how to calculate your buffer:
- Determine your weekly consumption rate. How many stamping parts do you use or sell per week?
- Multiply by 10. That is your target buffer quantity.
- Subtract current inventory and in-transit stock. The difference is what you need to order.
- Place the order by mid-October. This gives your supplier enough time to produce and ship before the pre-Tết congestion begins.
Staggering Orders to Manage Cash Flow
One concern buyers raise is that building 10 weeks of buffer ties up a lot of cash. This is where staggered ordering helps. Instead of one massive purchase order, break it into two or three shipments spread over October through early January. This approach reduces your cash flow exposure while still ensuring you have adequate coverage.
At DEWIN, we offer open account payment terms of 60 to 90 days to our U.S. clients precisely because we understand this cash flow pressure. When a buyer needs to front-load inventory for Tết, flexible payment terms make the strategy financially viable.
Supplier Diversification as a Safety Net
Relying on a single stamping factory in Vietnam 8 creates concentration risk during Tết. If that factory experiences a delayed restart—due to equipment issues, labor shortages, or raw material delays—you have no fallback.
We recommend maintaining relationships with at least two qualified stamping suppliers. Ideally, they should have different Tết shutdown schedules. Some factories in southern Vietnam close for shorter periods than those in the north. Knowing these differences lets you stagger production across suppliers and reduce the total gap in manufacturing capacity.
A Pre-Tết Inventory Checklist
Here is a checklist our project managers use with clients every year:
- Q1 demand forecast finalized by September
- Buffer stock quantity calculated and approved
- Purchase orders issued by mid-October for buffer stock
- First buffer shipment dispatched by late November
- Second buffer shipment dispatched by early January
- All pre-Tết shipments cleared through customs by late January
- Post-Tết production restart confirmed with supplier
- First post-Tết shipment tracking number received by early March
What About Air Freight as a Backup?
Air freight can rescue you in an emergency, but it is not a strategy. For stamping parts—which are heavy, metal components—air freight costs 9 are punishing. A bracket that costs $0.50 to ship by ocean might cost $3.00 to $5.00 by air. Use air freight only as a last resort for critical shortages. The far better approach is disciplined inventory management and early order placement. This is how you prevent Vietnam holiday delays without financial pain.
Conclusion
Lunar New Year is not a one-week holiday for your supply chain. It is a 6-to-8-week structural disruption that demands early planning, clear communication, and disciplined inventory management. Start preparing months ahead, and your stamping parts will arrive on time. For a deeper look at overall transit expectations, learn how long it takes to receive stamping parts from Vietnam so you can set realistic baselines before factoring in holiday disruptions.
Frequently Asked Questions
What About Air Freight as a Backup?
Air freight can rescue you in an emergency, but it is not a strategy. For stamping parts—which are heavy, metal components— air freight costs 9 are punishing. A bracket that costs $0.50 to ship by ocean might cost $3.00 to $5.00 by air. Use air freight only as a last resort for critical shortages. The far better approach is disciplined inventory management and early order placement. This is how you prevent Vietnam holiday delays without financial pain.
How can I plan my stamping parts orders around Vietnam's Lunar New Year shutdown?
A lesson we learned early in our Vietnam operations is that planning for Tết cannot start in January. By then, most factory capacity is already spoken for, and the window for securing production slots has closed.
What delivery delays should I expect when sourcing stamping parts during Tet holiday?
One of our U.S. clients once assumed a 5-day delay for Tết and planned accordingly. The actual delay was 38 days. That experience shaped how we now brief every new customer on realistic timelines.
Footnotes
1. Authoritative Wikipedia entry for Saigon Port, which encompasses the primary Cat Lai terminal. ↩︎
2. Authoritative overview of the Vietnamese Lunar New Year (Tết) holiday and its cultural significance. ↩︎
3. Authoritative Wikipedia overview of metal stamping processes, techniques, and industrial applications. ↩︎
4. Technical definition and industrial context for the metal stamping manufacturing process. ↩︎
5. Professional association resource for metalforming industry standards and die maintenance best practices. ↩︎
6. Comprehensive Wikipedia entry on the metallurgical processes used in heat treatment. ↩︎
7. Comprehensive industry guide explaining the types and applications of custom metal stamped components. ↩︎
8. Government resource regarding manufacturing supply chain resilience and risk management strategies. ↩︎
9. Official resource from the global air transport authority regarding international cargo and logistics. ↩︎