How Does Tet Holiday Affect Delivery Times for Stamping Parts from Vietnam?

July 16, 2026

Production floor at Van Mai Khoi, a DEWIN-audited Vietnamese factory

Tet holiday impact on Vietnam stamping parts delivery schedules

Last January, three separate U.S. clients contacted our Vietnam office in a panic — their stamping parts shipments were stuck, and nobody at the factory was answering the phone.

Tet holiday affects delivery times for stamping parts from Vietnam by adding 2–4 weeks of delay. Lunar New Year factory closures last 1–2 weeks, but the total supply chain disruption spans 3–4 weeks when you include pre-holiday congestion, workforce migration, and post-Tet production ramp-up.

This is not a small inconvenience. For purchasing managers running tight production schedules in the United States, a single missed delivery window during Tet can cascade into weeks of downtime. Below, I will walk through exactly how this holiday disrupts your stamping parts supply chain and what you can do about it.

How can I plan my production schedule around the Tet holiday shutdown in Vietnam?

One lesson we learned early on with our Vietnam office is that planning around Tet is not about the official holiday dates — it is about understanding the full operational timeline that surrounds them.

To plan your production schedule around Tet, work backward from the holiday by at least 6–8 weeks. Confirm all drawings, artwork, and material specifications early. Place orders and approve samples before mid-December to ensure your stamping parts ship before the pre-Tet logistics congestion begins.

Production planning timeline for stamping orders before Vietnam Tet shutdown

Understanding the Real Tet Timeline

Most people assume Tet is a 5–7 day holiday. On paper, that is correct. But the operational reality for metal fabrication lead times is very different. The disruption follows a predictable three-phase pattern that spans roughly a full month.

Phase Duration What Happens
Pre-Tet Acceleration ~2 weeks before Tet Factories rush to complete orders. Port congestion spikes. Domestic trucking for steel coils 1 disappears 3–5 days early.
Full Shutdown 1–2 weeks Factories close completely. Logistics providers suspend operations. No production, no shipping.
Post-Tet Ramp-Up ~2 weeks after Tet Workers slowly return from hometowns. Production runs at reduced capacity. Quality issues can arise from cold-start tooling.

The total impact is 3–4 weeks of supply chain disruption. If your stamping parts order falls anywhere inside that window, you will face delays.

Why the Pre-Tet Rush Hurts Quality

In the two weeks before Tet, our team in Vietnam sees factories pushing hard to finish every order on the floor. Workers are eager to collect their annual Tet bonuses and head home. This rush creates a production backlog that can compromise quality.

Precision stamping dies require thermal stabilization. When a factory rushes a final batch 2 and then shuts down for two weeks, the dies cool completely. The first post-Tet production runs often show dimensional variances 3 because the tooling has not reached its proper operating temperature. I have seen first-article inspection 4 failures after Tet that added another two weeks to already delayed schedules.

Build Your Calendar Around These Milestones

Here is the practical timeline we recommend to our U.S. clients:

Milestone Target Date (Relative to Tet)
Finalize drawings and specifications 8 weeks before Tet
Approve samples and sign off on PPAP 6 weeks before Tet
Complete mass production 3 weeks before Tet
Ship from Vietnam port 2 weeks before Tet
Arrive at U.S. port Tet week or shortly after

If you miss the "approve samples" window, your production gets pushed to after Tet. That alone can delay your launch by 4–6 weeks. The earlier you lock in specifications, the better your chances of staying on schedule.

The Raw Material Double Jeopardy

There is another risk many buyers overlook. If your stamping parts require specific steel grades sourced from China, you face a double supply chain disruption. China observes the same Lunar New Year 5 period. Chinese steel mills and coil suppliers shut down on nearly identical dates. So your Vietnamese stamping factory cannot even receive raw materials during this window. This makes early material procurement essential — not optional.

✔ The total Tet supply chain disruption for stamping parts spans 3–4 weeks, not just the official 5–7 day holiday True
Pre-holiday logistics congestion, the shutdown itself, and post-holiday workforce shortages combine to create a disruption window that far exceeds the calendar holiday.
✘ Vietnamese factories only close for the exact official Tet holiday dates and resume normal production immediately after False
Most factories close for 1–2 weeks, and post-Tet ramp-up takes an additional 1–2 weeks due to labor shortages from workforce migration back to rural provinces.
Video: Sample metal parts from audited Vietnamese factories in the DEWIN network. (@dewintech)

What lead time buffer should I add for stamping orders placed before or during Tet?

A buyer in the Midwest once told me he added one week of buffer for Tet and thought that was generous. His order arrived six weeks late. That experience taught both of us a hard lesson about how much padding is actually needed.

For stamping orders placed within two months of Tet, add a minimum 4–6 week lead time buffer. Orders placed during or immediately after the holiday may need even longer buffers due to production backlog, labor shortage, and port congestion at major Vietnamese export hubs like Cat Lai and Hai Phong.

Lead time buffer recommendations for stamping orders during Tet holiday season

How Much Buffer Depends on When You Order

The amount of buffer you need is not a fixed number. It depends on when your purchase order lands relative to Tet. Here is a breakdown based on what we have experienced managing orders through our Vietnam team:

Order Placement Timing Recommended Lead Time Buffer Reason
3+ months before Tet Standard lead time (no buffer needed) Production and shipping complete before disruption window
6–8 weeks before Tet +2–3 weeks Pre-Tet congestion may delay shipping; factory rush may affect quality
2–4 weeks before Tet +4–6 weeks Factory may not start production; order likely pushed to post-Tet
During Tet +5–7 weeks No production or logistics activity; full ramp-up delay applies
1–2 weeks after Tet +3–4 weeks Skeleton crew; slow production restart; freight forwarding backlogs

The Hidden Costs of Insufficient Buffer

When you underestimate the buffer, the consequences go beyond late delivery. Here is what typically happens:

First, your safety stock runs out. If you relied on just-in-time inventory, you have no parts to feed your assembly line. Second, expedited ocean freight or air freight to make up lost time is extremely expensive — especially when port congestion at Cat Lai or Hai Phong has already tightened capacity. Third, rushed post-Tet production increases reject rates. We have seen dimensional issues on stamping parts when factories restart cold dies without proper warm-up cycles.

Freight and Logistics Considerations

Logistics costs spike during the pre-Tet period. Carriers prioritize high-margin consumer goods over industrial shipments. Specialized heavy-haul trucking for steel coils — the raw material your stamping factory needs — often disappears 3–5 days before the official holiday begins. This cuts off raw material flow before the factory even closes.

Export customs clearance at Vietnamese ports slows down as government offices reduce staffing. Containers get "rolled" — bumped to the next available vessel — more frequently. If your freight forwarder does not book vessel space early, your stamping parts may sit at the port for an additional week or more.

A Word on Tet Bonus Amortization

Something many U.S. buyers do not realize: Vietnamese labor law requires employers to pay substantial annual Tet bonuses. Many suppliers quietly amortize this cost into the unit price of Q1 stamping orders. You might not see a line item for "Tet bonus surcharge," but the per-piece cost in January and February can be slightly higher than the rest of the year. Ask your supplier directly about this during contract negotiation.

✔ Orders placed within two months of Tet need a 4–6 week lead time buffer for stamping parts from Vietnam True
Factory closures, workforce migration, pre-Tet logistics congestion, and post-Tet slow ramp-up combine to extend standard lead times significantly beyond the official holiday period.
✘ Adding one extra week of buffer is sufficient to account for Tet holiday delays on industrial stamping parts False
One week only covers the official holiday. It ignores pre-Tet port congestion, carrier suspensions for heavy goods, post-Tet labor shortages, and production ramp-up time, which together add 3–6 weeks of delay.

How do I communicate with my Vietnamese supplier to avoid delays caused by Tet?

During our first year managing projects in Vietnam, we assumed that sending an email with delivery expectations would be enough. It was not. The cultural and operational context around Tet demands a different communication approach.

To avoid Tet-related delays, initiate direct communication with your Vietnamese supplier at least 8 weeks before the holiday. Confirm production milestones, shipping cutoff dates, carrier schedules, and post-holiday restart timelines in writing. Assign a local point of contact if possible to monitor progress in real time.

Effective supplier communication strategies to prevent Tet holiday shipping delays

Why Standard Communication Fails Around Tet

Tet is the most important cultural event in Vietnam. In the weeks leading up to it, the entire country shifts focus. Factory managers are coordinating worker bonuses, planning family gatherings, and wrapping up the year. Email response times slow down. Phone calls go unanswered. Decision-making stalls.

This is not a sign of unprofessionalism. It is a cultural reality. But if you are a purchasing manager in the U.S. waiting for a sample approval or a shipping confirmation, the silence can be alarming.

What to Communicate and When

Here is the communication checklist our team uses every year:

8 weeks before Tet: Contact your supplier to confirm the exact shutdown dates. Ask for the production schedule and when your order will be completed. Confirm all drawings, Pantone colors, and material specifications are finalized. Late artwork confirmations at this stage push sampling to after Tet and can delay your launch by 4–6 weeks.

4 weeks before Tet: Request a progress update. Ask for photos or inspection reports of in-process parts. Confirm the shipping date and the freight forwarding arrangement. Verify that the carrier you plan to use has not already announced a suspension date for bulky or heavy shipments.

1 week before Tet: Get final confirmation that your shipment has left the factory. If it has not shipped, discuss a realistic post-Tet ship date. Do not expect responses during the holiday itself.

1 week after Tet: Reach out to confirm the factory has reopened and your point of contact is back. Ask about the workforce return rate. If only a skeleton crew is back, expect reduced output for another week or two.

The Value of a Local Team

This is where having on-the-ground presence matters. Our seven-person office in Vietnam can walk into a factory, check production status, and escalate issues face-to-face. If you do not have a local team, consider working with a sourcing partner who does. Relying solely on email communication from 12 time zones away during Tet is a recipe for surprises.

A local presence also helps with export customs clearance. When paperwork issues arise at the port during pre-Tet congestion, having someone who can visit the customs office and resolve problems in person saves days.

Are there ways to keep my supply chain running smoothly despite the Tet holiday closure?

We once helped a client maintain an unbroken supply of stamping brackets through three consecutive Tet seasons without a single stockout. It required planning, but it was entirely achievable.

Yes — you can keep your supply chain running smoothly during Tet by building safety stock 6–8 weeks in advance, diversifying your supplier base, pre-booking freight capacity, and establishing clear post-holiday restart protocols with your Vietnamese stamping partner.

Supply chain resilience strategies for smooth operations during Tet closure

Strategy 1: Build Safety Stock Early

The most straightforward way to avoid a gap in your stamping parts supply is to build a safety stock buffer 6. Calculate your consumption rate for the 4–6 week disruption window and place orders early enough to have that inventory on hand before the Lunar New Year factory closures begin.

This means your purchase order needs to land at the factory no later than early December for a late-January Tet. The parts need to be produced, inspected, and shipped before the pre-Tet logistics crunch hits.

Strategy 2: Diversify Your Supplier Geography

If all your stamping parts come from a single Vietnamese factory, you have a single point of failure during Tet. Consider qualifying a secondary supplier in a country that does not observe the Lunar New Year — or at least one that observes it on different dates.

However, be cautious here. If your backup supplier is in China, they observe the same holiday. Taiwan also celebrates Lunar New Year, though factory closures tend to be shorter. India, on the other hand, does not observe Tet and can serve as a true alternative during this period.

Strategy 3: Pre-Book Freight and Logistics

Ocean freight capacity 7 tightens significantly in the weeks before Tet. Freight forwarding companies get overwhelmed with last-minute shipments. To avoid having your stamping parts sit in a warehouse or get rolled to a later vessel, book your shipping slot 4–6 weeks in advance.

Work with your freight forwarder to confirm:

  • Vessel booking dates and cutoff times
  • Container availability at your departure port
  • Any surcharges for peak-season shipping
  • Estimated transit time to your U.S. port

Strategy 4: Plan for Post-Tet Die Maintenance

This is a detail most buyers miss. The Tet shutdown is when Vietnamese stamping factories perform deep preventive maintenance 8 on high-volume dies. If the maintenance crew discovers unexpected tool fatigue — cracked inserts, worn guide pins, eroded punch tips — the first post-holiday production runs can be delayed by weeks.

Ask your supplier before the shutdown: What is the die maintenance plan? Are spare die components on hand? What is the expected timeline to resume production at full capacity?

Strategy 5: Use Credit Terms to Your Advantage

One advantage we offer our clients is open account payment terms 9 — typically net 60 or net 90 days. This is especially valuable around Tet because you can place larger pre-Tet orders to build safety stock without straining your cash flow. You receive the parts, use them, and pay after the holiday disruption has passed.

Quick Reference: Tet Supply Chain Survival Checklist

Action Item Timing
Finalize all part specifications and drawings October–November
Place safety stock order Early December
Approve samples and complete PPAP Mid-December
Book freight forwarding and vessel space Late December
Confirm production completion and ship date Early January
Verify shipment has departed Vietnam 2+ weeks before Tet
Confirm factory restart and workforce return 1 week after Tet
Resume normal ordering cadence 3–4 weeks after Tet
✔ Building safety stock 6–8 weeks before Tet is the most reliable way to prevent supply gaps for stamping parts True
Pre-positioning inventory before the disruption window begins eliminates dependence on factory production and logistics availability during the most congested period of the year.
✘ E-commerce platforms in Vietnam continue delivering industrial stamping parts without delays throughout Tet False
While consumer e-commerce platforms like Shopee claim uninterrupted service, industrial heavy goods — including stamping parts — are explicitly flagged for suspension by major carriers as early as February 9, and actual delivery depends on third-party logistics firms that reduce or halt operations.

Conclusion

Tet holiday delivery delays for stamping parts from Vietnam are predictable and manageable. Plan 6–8 weeks ahead, build safety stock, communicate proactively, and partner with a team that has local presence in Vietnam. For broader guidance on how to handle supply chain delays when sourcing stamping parts from Vietnam, understanding the Tet disruption cycle is an essential first step. You can also learn more about how long it takes to receive stamping parts from Vietnam under normal conditions to better calibrate your planning.


Frequently Asked Questions

How can I plan my production schedule around the Tet holiday shutdown in Vietnam?

One lesson we learned early on with our Vietnam office is that planning around Tet is not about the official holiday dates — it is about understanding the full operational timeline that surrounds them.

What lead time buffer should I add for stamping orders placed before or during Tet?

A buyer in the Midwest once told me he added one week of buffer for Tet and thought that was generous. His order arrived six weeks late. That experience taught both of us a hard lesson about how much padding is actually needed.

How do I communicate with my Vietnamese supplier to avoid delays caused by Tet?

During our first year managing projects in Vietnam, we assumed that sending an email with delivery expectations would be enough. It was not. The cultural and operational context around Tet demands a different communication approach.

Footnotes


1. Authoritative industry association providing information on steel markets and raw material supply chains. ↩︎


2. Explains the batch production method used in stamping and how it is affected by factory shutdowns. ↩︎


3. Technical explanation of engineering tolerances and dimensional accuracy in manufacturing. ↩︎


4. Explains the quality control process referenced when discussing post-Tet inspection failures. ↩︎


5. Clarifies the holiday buyers must plan around when evaluating alternative suppliers. ↩︎


6. Defines the inventory management concept central to avoiding Tet-related supply gaps. ↩︎


7. Provides background on freight logistics affected by pre-Tet shipping congestion. ↩︎


8. Explains the systematic approach to equipment upkeep used during factory shutdowns. ↩︎


9. Explains the trade financing arrangement used to manage cash flow around Tet. ↩︎

Manufacturing RFQ

Have a STEP Model or 2D Drawing for This Project?

Share your drawing, material, quantity and finishing requirements to begin a manufacturing quote. Confirm pricing, delivery and inspection requirements during the review.

Upload CAD & Get Quote →